Worked scenario
Example: two activities weighted 60% and 40%, with actual progress 50% and 25%, give total weighted progress of 40%.
Free physical progress measurement dashboard. Calculate weighted planned and actual progress from activity weights, compare the variance and plot the S-curve.
| # | WBS / No. | Activity Description | Weight (%) | Planned Start | Planned Finish | Planned % | Actual % | Progress (Plan vs Actual) | Variance (pts) | Status |
|---|
Free physical progress measurement dashboard. Calculate weighted planned and actual progress from activity weights, compare the variance and plot the S-curve.
Use the dates, quantities and currency shown in the workspace. Keep one currency and a consistent reporting cut-off.
Compare planned and actual physical progress using activity weights. Cost expenditure is not a substitute for installed quantities.
Method: the owner’s supplied worksheet and the arithmetic described above.
Illustrative inputs for checking the method; these are not project records.
Example: two activities weighted 60% and 40%, with actual progress 50% and 25%, give total weighted progress of 40%.
Free physical progress measurement dashboard. Calculate weighted planned and actual progress from activity weights, compare the variance and plot the S-curve.
Use the dates, quantities and currency shown in the workspace. Keep one currency and a consistent reporting cut-off. Compare planned and actual physical progress using activity weights. Cost expenditure is not a substitute for installed quantities.
Use the save, export and print controls shown in this workspace. Where CSV export is available, the exported data can be opened in a spreadsheet. Browser print can save a PDF.